This is the story of the purchase and renovation of Matthew & Jane's house somewhere in the heart of England, following Matthew’s redundancy in 2010 at the age of 58. Said to be from c.1835, we first saw it in Aug 2010. It had been empty for only a few weeks but was pretty awful due to dampness and long term neglect. Locals thought it had been uninhabited for years and was only fit for demolition! But we bought it anyway and moved in after 8 months work in July 2011.
Friday, 24 February 2023
Relaying the Hall Floor (Part 3 of 3)
The hall was laid by my friendly professional - I knew that I would be lucky to achieve a job half as good as he has done, so it was well worth it. We used some stuff that I had not encountered before, called "AdhereCal". It comes in powder form like NHL but, when mixed, it looks like a fine lime plaster which is sticky like normal tile cement. It has certainly done the job for us, although there was a minor panic when he ran out and I was 25 miles away. Luckily I knew where one of the few local stockists was and was able to get there before they closed.
These photos show the finished result, with which I am very pleased - and so is t'other half, which is probably more important.
This is a close-up showing the corner of the hall in front of the front door.
The photo left shows the view after entering the front door and turning right to see the way through the arch, while the one below shows the view back from the stairs towards the front door and the arch, with the hall window behind the arch.
I have often been asked when the house will be finished. My standard answer is that, as far as I am concerned, the house moved from "restoration and landscaping" to "maintenance and gardening" in about 2013. However, now that the hall floor is finished, I really do hope people stop asking me that question.
The only things to be done are things that I have done before! The bathroom fan has been replaced, we have a new fridge, we had an new washing machine about 5 years ago (don't buy a Haier - there are no spares available), I have re-decorated the hall and lounge walls, I have re-built the cheap shed which I bought in a hurry in 2011 to keep things dry.
Friday, 27 August 2021
Relaying the Hall Floor (Part 2)
The new limecrete (NHL5) screed is laid (left) over the recycled foamed glass, and I have done a scratch coat on the lime plaster (below) where the old concrete skirting board was.
But things do move on slowly at times, like when you are waiting for the NHL to set completely, or when waiting for the scratch coat of lime plaster on the wall to go off so you can do the second coat.
The English limestone flags arrive today, I hope, but they cannot be laid for at least another couple of weeks, but it's more like three weeks - first it's the wait for the floor to be ready then - guess what? - the contractor has a planned commitment for 9 days on September 6th which means we are waiting until almost September 20th.
However, with a small delay the water pipe was fixed two weeks ago now. I am really glad that it was noticed as it would have gone sooner or later. The cost was probably an additional £750 (plumber and builder together). I can only guess at how I would have felt if, in a couple of years, the new floor had suddenly become very damp and we would have to done the job, cursing, at even greater expense.
I have also sold the Staffordshire Blue tiles for a reasonable price. They went to a flooring contractor who was going to lay them in a couple of days time in a house in London. Sadly I could not interest him in the collection of red quarries I have.
One job I can do is to paint the skirting board which has already been delivered. The profile matches what we have in the lounge which was made for us in 2011, so t'other half is very pleased. Result!
Friday, 13 August 2021
The Corroded Rising Water Main
It might have been only precautionary (and also expensive) but I am sure that, in a year or two, we would have had a massive leak in the hall; if we had continued and done the floor, that would have been most annoying and a lot more expensive!
No further comment or comment is neccessary!
Thursday, 12 August 2021
Relaying the Hall Floor (Part 1)
The current floor is (I reckon) the original from the conversion of the school to a house in about 1861; the photo (right) shows it as it was in 2010. We left a small part of the old floor near the under-stairs cupboard (left of the stairs in the photo) as it's not in bad shape.
The limecrete floor will be constructed with a base layer of "Geocell" Recycled Foamed Glass (RFG) (see www.mikewye.co.uk/limecrete-floors/) as opposed to the Light Expanded Clay Aggregate (LECA) which I used for the kitchen floor (see entries in March/April 2011).
The RFG (being loosely laid, left) has several benefits (compared to LECA), one of which is that the depth of the floor is less and hence there is less to dig out! I have already been caught out by the volume of the removed floor - it seems to have expanded massively (like, doubled) in volume and so is filling more bags that I expected! It was very well compacted.
We have also removed the horrible concrete skirting (which was painted BROWN before we moved in! I re-did it in white) which will be replaced by some pretty profile in pine to match what I fitted in the lounge.
The removal of the old floor left a huge hole between the door to the lounge (at the front of the house) and the door to the kitchen/diner (at the back). I solved this by fitting a bridge using two 3 metre bits of 75mm x 50 mm C16 covered with bits of old floorboard from the firewood pile.
As an added refinement, I have covered the boards with a piece of carpet (as laid on the stairs and landing); the stairs are easily accessed from the bridge.
An unforeseen problem: in one corner of the hall we uncovered the mains water supply (which I knew was there but had ignored for the last 10 years) - photo below.
Below the tile level it was badly corroded and so it has to be done NOW, not later; so now outside there is a large hole and I have a plumber coming on Friday to fit a plastic pipe through the wall to the mains supply outside the house (photo below - note how the water pipe comes out from the wall and goes under the rainwater drain at an angle). More expense but it's worth it (as I keep telling myself).
The original plan was to re-fit as many as possible of the existing tiles supplemented by similar ones bought at local reclamation yards. Sadly, yesterday I took my other half to a reclamation yard as I needed to buy some more reclaimed tiles - the re-useability of the lifted ones is just over 50% (even worse than I had gloomily expected).
This visit was a mistake - first I was gently told off by the owner for sorting out suitable good condition tiles (!), so I didn't buy any at all. Then, second, once the other half had seen for herself the difficulty of finding acceptable old quarries, she decided that we should buy some proper stone flooring instead. Aaargh!
So I now have available a large number of mostly one inch, good clean reclaimed quarries (a variety of red, red/orange, proper Staffordshire blue and other blue/black), plus a lot of good ones waiting to have their grouting etc removed, plus a lot more of rejected ones (suitable for outside use only). At least I don't have to do any more grouting removal and also the retained small part of the original floor will now be done as well.
These are actually the old tiles in 2010 - the ones I have now are not quite as bad!Sunday, 4 July 2021
A Real Work of Art - in our house!
The panels in question are in the standard old four-panel pine door to a north facing bedroom. I guess that the old wooden panels were replaced a long time ago in a bid to shed some light on the stairs which otherwise have no natural light. The glass used was about 4mm thick and one side has vertical grooves to distort the image from the outside. The trouble was that it was impossible to get old paint and varnish off the edges and especially from out of those grooves, so they always looked dirty. Interestingly, the plain side of those glass panels is actually wavy, so I have no idea how old they are.
Strictly the new windows are coloured and leaded glass (and not painted glass), but everyone calls this "stained glass". Here are some photos of what we now have and the old glass.
It's quite difficult to get a decent photo from the stairwell, but the left picture shows the colours cast on the door surround, and they also appear on the yellow clay paint of the stairwall.
The old panes, removed without breakage!
This shows the wavy nature of the old glass.
Thanks to Themis Mikellides at Bath Aqua Glass who made the windows for us.
Saturday, 2 May 2020
Sometimes I am Truly Blessed
Let me tell you what happened: the church has had a new wooden floor put in and fixing the old tiles which are right alongside the new floor was not in the contract, so Muggins here gets the task (as always) of making good the little gap. Naturally, in some places the repair had to be more than a single tile as things like that always get loosened by, in one case, a friend who simply "forgot" that he MUST NOT TREAD NEAR THE EDGE!
I was using a 4.5 inch grinder on some Victorian floor tiles to get them to fit. You have to remove any grouting around the edge and make sure that it fits properly. I had done loads of those, and then had to sort out a few small pieces to insert into the floor. Where there is a triangular corner piece (with the two shorter sides at 2 inches), and the adjacent tiles are still well attached, you don't really have any choice unless you want to relay the entire floor: I am using an adhesive to fit tiles like that, but the issue was that the piece of tile was too thick. Solution: grind a small amount (5 mm, perhaps) off the underside of the tile.
Thus, well knowing the dangers of this job, I found a piece of 6" wood and clamped the piece of tile to it, using a G-clamp. I could then put a foot on the piece of wood (because my workmate is in the church and I was at home) and safely grind away the necessary, with two hands on the grinder. Gloves on, goggles on, what could go wrong?
So I was happily doing this when it all did go wrong. I think the grinding wheel touched the G-clamp which caused the grinder itself to be twisted in my hands and somehow hit the BACK of my right hand which had been holding the side handle. My left hand was still holding the main body of the grinder and I threw it away, just as I noticed the blood literally pouring through the glove. I left a bloody trail into the kitchen and staunched the flow with cold water and kitchen towel.
The resulting cut was about 2cm long, on the back of the base of my right thumb, about 5cm below the edge of the bit of skin between thumb and forefinger. Have a look at your own hand and see if you can identify the main tendon on the back which operates your thumb. Well, the end of the cut was at right angles to the tendon and about 5mm from it - yes, less than 0.25 of an inch! Near the left end of the cut there was another tendon less that 10mm from the cut.
Google tells me that these tendons are called the extensor pollicis longus and the extensor pollicis brevis, and it is a complete mystery to me how they are still in one piece. Somehow I had let a grinding disc attack my hand and go right through all the skin layers at right angles BETWEEN two most important tendons! As the doctor at A&E said as she inserted four stitches, "You are very lucky" - or perhaps Someone is looking after me?
A week later I had the stitches out and two days later you can hardly see the scar.
Tuesday, 11 June 2019
A New Back Gate
were previously doors, one from the house and the other acquired as a swap for some old glass. The latter one was always a problem as the white paint was very tough to sand and in fact was probably impervious, so kept any water in as well as out! I never painted the garden side of it for that reason, so it was black on the public side and white on our side.
Last year I saw that the black and white gate was rotting and I replaced the upper ledge in situ. Then this year I realised that the rot was worse than I thought; the new ledge was about the only decent bit of wood on the gate, with both braces and the two old ledges all looking bad. Moreover, some of the T&G was bad, especially the edge where the two gates almost meet. I haven't bothered with photos of the rotten wood - I'm sure you are familiar with that!
Feeling adventurous, I purchased some 6x1 inch treated "as-sawn" timber and, after some serious sanding, set about replacing parts of the gate in sequence. First I made two new
ledges, replacing the middle one first and then securing the two gates together (using spare wood and screws) while I replaced the bottom ledge which carried the lower hinge. Then I had to remove the first two planks from the latch side of the gate as they were narrower than the replacement board. (See top photo)
When the first plank was fitted I removed the next old one and fitted the second new one, and so on. The only real difficulty with this was that the hinge screws had penetrated through the ledge to the planks, so I had to be careful when doing the planks closest to the hinges as the gate then felt a little wobbly with these screws removed.
The other necessary trick was to work out where the hinge screws would go and, of course, one of them was right into a join between two new planks.
The penultimate plank required me to rip a narrower plank to
allow the last plank to be full size with two good edges. Then I cut two new braces which were added after the third photo on the right.
Anyway, it's finished now, complete with four coats of primer/undercoat/top coat and I'm very pleased with it!
Havng used treated timber I don't expect to have to do much maintenance to it, other than clean the bird muck off it - I'm wondering whether bird spikes on top would look silly or OK?
Wednesday, 24 April 2019
Fame at Last
The book is selling well and a further print has been made! There's still a long way to go before every churchwarden in England has read a copy.
Saturday, 15 December 2018
Rotas Rules and Rectors
This book is aimed at helping existing Anglican churchwardens to understand the job better and even thrive while doing it. I hope that it will also both encourage potential churchwardens to stand for nomination and discourage the no-hopers who get elected and then stop after one dismal year as they didn't know what they were getting into.
In my view the published books which purport to be on this subject only cover the legalities of elections and meetings etc, and fail to cover the actualities of what you need to do. This book covers that sort of thing using my own experience of 11 years in the job at two different churches since 2005.
"Rotas Rules and Rectors" is published by Matador (ISBN 9781789016314) and is available widely on-line (just search for the short title), but please buy from my own website www.beingachurchwarden.com if you want a copy as that will maximise the profit to my church's re-ordering fund. I am currently offering it at £7.99 (which is £2 off the RRP) plus £1.95 P&P.
You can also find more details of the book, including extracts and author details, at www.beingachurchwarden.com.
Follow me on Twitter @AChurchwarden and Facebook @beingachurchwarden
Monday, 20 August 2018
The Last Sash Window - Pictures
Well, at last I've done the fiddly bits on the last sash window,and so the job is effectively finished and I can now post a few photos. Firstly, here's what it looked like before we bought the place (first seen in August 2010).
Then, here's what it was like after removal of the ivy (and we moved in - July 2011):
Here's what it was like after a quick coat of paint on the (concrete) cill and the fake stucco (probably later in 2011, or else in 2012):
Finally, here's the finished product (2018):
As you can guess, I am pretty pleased with the result, especially as the old wavy glass can really be appreciated when it catches the reflections and, of course, the fact that both windows work as intended!!
I am now certainly qualified to give advice on refurbishment of Victirian sash windows, having started with absolutely zero knowledge.
Edited 25 Aug 2018: I just found that I made a miscalculation. I added a nice brass latch and a solid brass handle to each of the windows, and then found that one of them wouldn't stay in place as it did before. Clearly my weighing to make my lead weight was too accurate as it didn't take account of the brass handle, which has now been removed. Drat!
Sunday, 15 July 2018
The Last Sash Window
The window concerned was the front window with two lights, both just one over one, separated by a cement mullion on the outside; this window is for the bathroom/loo upstairs. The top pane on each side is a rectangle with a half round at the top, and I checked with my glass supplier that he was able to cut such a shape (just in case I broke one) but in fact both those came out OK. The top pane on each side was a fixed window, lacking pulleys and cord, and in fact some of it was unpainted - obviously it had been installed unpainted, so had probably never been removed in 150 years.
All my sash windows have needed a complete renovation. All of the latches were solid and unusable, all the pullies except one* were worn out, with huge gaps between the spindle and the housing, most windows were painted in solidly, the bottom half of the putty was usually falling out, and only about six cords were intact out of 24. So the complete renovation involves removing all glass and brass, strip to bare wood, repair as required, paint, fit same glass with fresh putty and refit with new cord, new pulleys and new latches.
I had one issue as three of the weights were locally cast lead (2.1 lb) and one was a standard 6.5 lb iron one, just like the rest on the house. The issue I had was that I could not get the iron one out easily. Eventually it came when I worked out a way of levering it out longitudinally, forcing the gap apart a bit. When it came to re-instating the window, I made a new one out of lead sheet, wrapped around a long plated screw. This was made at the same weight as the others, because I was using the correct thickness of glass; the 6.5 lb was serious overkill by some repairer in the past - that one weight was more than the required weight of two, and of course being on the one side it meant that the window would always have been sticking by being unevenly weighted.
By now I have got a good idea of how to do this job but even so I reckon that each complete window takes about 30 man-hours and an elapsed time of almost two weeks. Although this last window was smaller and one over one (all the others were two over two, with two frames), it is a double window with four frames so took me just as long as the larger ones.
So, this last window is basically done but I just need to re-instate the pointing and sort out the cills; I think I'll leave that for a couple of weeks time. I'll offer free advice on Victorian sashes but I hope I don't have to ever do another. Now, I have work to do on the church opposite in August, so I expect little more will happen on the house this year - the tiles in the hall floor are just about the last major job on the list.
* and that was only found serviceable after I had wrecked the face plate in getting it out!
Saturday, 23 December 2017
Another End of Year Review
Frankly, I don't feel I've done much here in 2017. I did accomplish the previously reported refurbishment of the two remaining large sash windows - both hard work but very satisfying to see (and feel the benefit of reduced draughts). I also managed to repair the corner of a back wall where many stones were loose - I was worried that if my neighbour's side was as bad then the wall might collapse but, fortunately, his side was better anyway. The rest of the list from earlier this year is still outstanding.
There has also been a lot of clearing out in the second bedroom where I have made a wardrobe. This clearing task was made much easier after August as our daughter's wonderful wedding dress was used for its intended purpose and now lives at her house. Otherwise my shed is now full of stuff from my Dad's house that I would like to use, restore or sell - that last task seems to be a lot more work than one might think. I have not done much in the garden except to keep it tidy; I was really annoyed when the people at the back started to cut the ivy on my back wall - I asked them to leave as much as they could as it breaks up the appearance of the wall and adds some privacy, as well as giving food and shelter for birds.When they finished, it looked the same on my side, but on their side they had given the bit on top of the wall a short back and sides - the vertical wall was totally clear and so all the ivy on top had been cut off from its roots! Sigh.
It might be considered that I must have been lying around doing nothing this year, but this is definitely not the case. Leisure wise, I have bought a one-tenth share in a small aeroplane which is older than I am, and refreshed my private pilot's licence, so there is a bit of flying to look forward to in 2018.
At the church, we have done a £250k job on the exterior, thanks to a grant from the Heritage Lottery Fund. In the course of this work we suffered some vandalism when some little sod got up the partially completed scaffolding before the alarm was fitted and literally kicked a couple of stained glass windows to pieces - this repair should be complete at last in early January. You can hardly imagine how much work is caused by an incident like that, and most of it fell on my shoulders.
That reminds me of something that I need to pass on about the erection of scaffolding. It appears to be customary trade practice not to fit a scaffolding alarm until the erection of the scaffolding is finished. Now, I can understand why that should be the case for scaffolding around a house, as the alarm will get in the way of the next day's erection work. However, when you are putting up 13 lifts of scaffolding around a church tower, the job will take several days so I cannot understand why the alarm cannot be fitted once you have done the first three or four lifts, as all subsequent work will be above the alarm. If I was the insurers I would be insisting on a change to the current practice, but fortunately they are paying (apart from our excess)...
At one stage recently, one of the two temporary plastic sheets fell out of the window and made everyone very cold for one weekend. To fix this, I hired a 7.2 metre double width scaffold tower which was erected and dismantled by me and two men of similar age. To my surprise, I found that the double width tower was no more difficult to erect
and, in fact, the platforms were easier to manage, so I will use one of these in future. The window job itself took only 25 minutes and our end result is much more secure than that of the professionals who fitted the stuff.
This year we have had a cruise from Jordan to Malaga through the Suez Canal, seeing Petra in Jordan and calling at Crete, Malta, Palma and Gibraltar; we also spent a week in Sicily in September, so we have done OK for holidays. (NB From our cruise we flew back from Malaga and had the most dreadful airport experience of our lives - don't go there! If it's a bad as that on a Sunday in early April, what was it like in August?)
We have become used to being in each other's company for most of the day, almost every day, now that we are both properly retired, and I expect to end my six years as Churchwarden in May 2018, so I will then have even more time on my hands.
Tuesday, 8 August 2017
Sash Window Surprise and Mystery
in the house - this one is in the hall (photo right), and there are still two small sashes in the bathroom to be done but they are one over one, so they hardly count. (NB The front door is at right angles to the window, behind the wall to the right.)Now, the weather this August has not been too good, and this week is no exception. Having identified this as the last two week period this year when the job could be done, I started yesterday but didn't get very far in that weather. In fact it was pretty depressing as, having been pretty successful in removing the old glass on the four similar windows which I have renovated in the last two years, yesterday I broke three panes on only the one sash. Now, since the window is 2 over 2, by definition one sash has only two panes - I broke both those and, in seeing if a spare piece of glass from a previous window would fit, I broke that too! However, today was better. I got both wavy panes out of the top sash unbroken, and also stripped both sashes to bare wood, including getting all the putty out.
The surprise was the discovery that the top sash has never been a moving window. It has no pulleys and weights, nor even an attachment point for any cords.
The mystery is that although it was quite difficult to get the top sash out, this was entirely
due to the fact that it had been generously painted in on several occasions - there was no other visible attachment holding it in place. No screws, no nails, no wedge, nothing. How did they do that?
Left is a picture showing the pulley for the lower sash and an unpainted piece of wood with no hole where it should be for the pulley for the upper sash!
Fortunately, when trying to free the upper sash with a Stanley knife, I was well aware that there might be no cords holding it, so I did the job very carefully. I was most relieved when I had it in my hands complete and undamaged, and even more pleased when I had both panes out safely an hour later.
Edit following completion of the task: Mystery solved! The top sash was originally held up by a pair of very fine nails - basically long panel pins - which were nailed upwards at an angle of 45 degrees at the bottom of each vertical part of the sash frame. These of course were ferrous and so had rusted away a long time ago; it took me a long while before I found the traces of the tiny rusty holes as I knew they had to be there somewhere!
I am very pleased to have had the whole window repainted, reassembled and working on the eighth day of this project; it took about 30 manhours and looks pretty good. I didn't bother to even take any photos of the stages as it was just the same as the earlier ones, apart from the fixed window. Now all I have left are two small one over one sashes which form the bathroom window - that's a project for next year.
Friday, 19 May 2017
Plan for the Year
Anyway, there are jobs to be done and the first is to make a list:
a. Sash windows - two large ones are left to be refurbished, and there is a smaller pair in the bathroom. Hopefully I will get at least the two large ones done this year - one is in the kitchen and the other is in the hall (but there is also some remedial work to do on one of last year's where some putty has slipped).
b. Plastering - I need to do the inset bit at the top of the hall window which is hanging, albeit still complete, plus the three inset bits around the main bedroom window. These bits were all not done in 2010/11 as they looked OK then, but they are showing signs of wear around the edges!
c. Garden walls - I have been doing some repairs to two of the garden walls, and this could continue for ages as they are in pretty poor condition. In many cases I have to remove several stones and carefully remortar them (with NHL3.5) so that they are set solid before I do the next bit above. There is also the front (side) garden wall which I found last year was bowing horribly towards my neighbour's garden - and it is about 10' high, so that's quite a worry. However, that rebuild won't happen this year...
d. The back garden needs lots of tidying where the residue of 2011's work is still apparent, and there's still some ground elder to dig up carefully.
e. Redecoration - I think that 'Er Indoors wants some redecoration in at least one of the back bedrooms and, possibly, the lounge.
I have done some things this year - the wardrobe in a back bedroom was completed back in February, which has allowed a rearrangement of the stuff in our main wardrobe. As another consequence, we have been able to dispose of some items of furniture.
I have also been helping my next elder brother and both my sisters to tidy our parents' house. Mum died in 2015 and Dad is now in a carehome with vascular dementia; at 95, clearly he will not be going home again. I think the house will need to be sold by early next year to pay for the carehome which is really quite expensive. As part of clearing that house in London I have occasionally brought things back home for disposal or sale - such items always take priority over mere house jobs and selling things on eBay is actually quite time-consuming, I think.
The major change this year is that my other half has retired from full-time work. This has been quite an adjustment for both of us, as I had been so used to her disappearing early in the day and arriving back much later in time for an evening meal (made by me); this routine allowed me to work out the day for myself as I wanted, but suddenly there is someone else wanting to use the car, or the bathroom, or whatever room I wanted to work in etc. You get the picture!
I've been retired for nearly seven years now, and haven't really stopped until the last year or so - at last, this is what retirement is really like?
Friday, 13 January 2017
More New Year Resolutions
The most momentous event of the year was that t'other half finally retired and so no longer travels to London each weekday; we are still trying to work out how to exist together for seven days per week, when for the last six years I have been accustomed to being on my own (and doing the shopping and cooking) for five of those days. We have already learned the benefits of not waking at 6.15am, and are still catching up on years of lost sleep!
Last year I did achieve most of my intentions:
a. The hall landing and stairs were painted in the Earthborn claypaint
b. I stripped, repaired and repainted one half of the back gates
c. I managed to renovate two more sash windows (the back bedrooms)
d. I installed a wardrobe in the second bedroom, using the doors and frame given to me by the neighbour who was throwing them out - I'm very pleased with the result
e. I built a second wood-store and also did a couple of similar jobs in the church
However, I still have the following to do this year:
1.There is still some plastering to do: the window recess in the front bedroom is some of the last original plaster left, and it doesn't sound good.
2. In painting the hall I found that the plaster in the top of the hall window recess was dropping down and so needs to be re-done as well, with lime plaster. It would make sense to do both 1 and 2 at the same time but that will make a mess in two places at the same time, and the job will want three or four coats with drying time between.
3. The wardobe in the front bedroom needs plastering (modern stuff - it's panelled with plasterboard).
4. I still want to put fire black on some fireplaces - I've never done that before and feel that it could be messy!
5. There are still two more of the same size sash windows (hall and kitchen) to do, plus the pair of small ones in the bathroom.
6. One very new job is that the high stone wall (between our neighbour's back garden and our front) needs to be rebuilt - it is about 8 feet high on my side, and about 10 feet on my neighbour's, due to the difference in ground levels. It has a lot of ivy damage and also leans alarmingly. I think I will get it done by a professional...
We have our daughter's wedding to look forward to in August, and have also booked a cruise from Aqaba to Spain just before Easter. Somehow I don't think the year is going to hang around!
Wednesday, 26 October 2016
Repairs to Large Stone Wall
The wall is of a mixed construction being partly coursed random rubble and partly roughly
squared - see photo (the bin is just there to give an idea of scale). Where it was clear of ivy (left of picture) there are mostly blocks with good pointing, which is why I thought the whole thing was in good condition; however, much of the rest is coursed random rubble. The whole is capped by 3" limestone slabs, 16" wide and about 30" long; these seem to have been set with a small slope for drainage. Now that the ivy is largely cleared (the darker area where the ladder is), it is apparent that the coursed random rubble is in pretty poor condition with loose or missing mortar, ivy penetrating the wall and loose stones in the first couple of feet down from the top.
The wall starts off pretty vertical (where it leaves the neighbours' house, out of the left side of the above picture) but moving away from the house it has a bow which means that the natural taper has become vertical on their side and a quite marked slope on mine. The top looks awful (left photo) but it's not possible to say what the original slope of the coping was; it has certainly increased a lot in places, but I don't have an clinometer so I can't measure it.
I've had a builder look at it and his view is that the bow means that the top has moved over a foot out of true, which is a lot, and so it looks as though the neighbours and I will have a discussion about this with a view to rebuilding the top few feet sometime next spring!
Friday, 22 July 2016
The Year is half over
We've now been here for five years, and that hardly seems credible either. I first saw this house at the start of August 2010, and it immediately spoke to me. Moreover, I knew that it would speak to my other half as well - she has the vision (so often lacking in those TV property programmes!) to look past the defects and the undergrowth, and to see what a place could be. We never had any real doubt that this was the place for us, and I can still recall the evening of the day we moved in - we shared a wonderful sense of peace and satisfaction that this was OUR HOME, in every sense of the phrase (despite the boxes, mess and work still outstanding).
Back to my questions above. Firstly, I have been mentioning about the internal doors since 2012 (when I did the door from the kitchen to the new extension); in 2013 I started on the three doors in the hall (filter on "decorating" or "doors" to find these posts) These are the original doors with four recessed rectangles, the upper pair being slightly larger; the doors were covered with some revolting brown stuff which gummed up sandpaper in two strokes and was eventually removed with a three handed operation involving a hot air gun, a scraper and a Stanley knife; the knife had to be used after every stroke to remove the molten globule from the scraper, otherwise the next stroke would leave as much as it removed. I managed this by holding both the heat gun and the Stanley knife in my left hand, at the expense of a slight strain to the thumb!
Compounding the difficulty of the brown gunk, both sides of the lounge door and one side of the kitchen door have a moulding around each of the four rectangles, which made removal of the gunk even more onerous. There was also the architrave around both sides of the kitchen door - I confess that in 2015 I gave in and replaced the architrave around the lounge door (which had been split on one side in earlier works although I forget exactly how).
Anyway, I stuck at the removal task and had done the two main doors by last autumn. Remaining was the door to the cupboard under the stairs, which I did in February this year. The nice touch on this one was to add a bit of architrave above it, which has improved the look considerably. They are finished in eggshell eau-de-nil which looks really good with the gentle yellow of the claypaint walls.
Secondly, I determined that there were some jobs for which I just had to bite the bullet, namely the sash windows. I did one (the largest and most complicated!) last year, and soon I'll post a detailed report on the ones I have done this year. Once again, my choice of window was thwarted - t'other half wanted me to start with the other bedrooms, and I wanted to do the bathroom small pair at the front. Anyway, the pretty large sash in both bedrooms is now complete and they really do look better. I estimated last year that the first one took me 60 hours; both these are not quite as large and have one glazing bar less, and took me about 40 hours each.
I have also built a second wood store outside, and have tackled a few of those little jobs that one puts off, like the bit of stone on the front corner which was missing (as someone had indented a bit of wood from the gate frame into the wall! WHY?). There remains for this year the two small sash windows in the bathroom, some lime plastering around two recessed windows and a new wardrobe in the second bedroom; that will leave just two sashes for next year. Perhaps then I will have to find new ways of enjoying my retirement!
Monday, 4 January 2016
Another Year
I did do a couple of things not listed in the last progress update last June or the end of year update immediately below this entry:
a. The hall landing and stairs were painted in the Earthborn claypaint and look lovely - I do recommend this stuff, but to get the best result you need to roll it rather than brush it.
b. I stripped, repaired and repainted one half of the back gates - as they are from different sources they wear differently, and the one half that I had renovated in 2011 was looking quite poorly. I think this was because it wasn't actually as dry as I thought then.
Now, in the coming year, there are a few big-ish jobs left:
1. The big question is how many sash windows I will renovate. My plan is to do at least the narrow pair in the bathroom, followed by the one in the hall. That will leave one in the kitchen and two in the back bedrooms.
2. There is also some plastering to do: the window recess in the front bedroom is some of the last original plaster left, and it doesn't sound good. Having done the window last year, it makes sense to tackle this tricky bit of work.
3. In painting the hall I found that the plaster in the top of the hall window recess was dropping down and so needs to be re-done as well, with lime plaster. It would make sense to do both 2 and 3 at the same time but that will make a mess in two places at the same time, and the job will want three or four coats with drying time between.
4. The wardobe in the front bedroom needs plastering (modern stuff - it's panelled with plasterboard).
5. I want to install a wardrobe in the second bedroom, but that means that I have to sort out a full four drawer filing cabinet and other stuff...
6. I'd like to put fire black on some fireplaces - I've never done that before and feel that it could be messy!
7. Then there's more decorating and other internal jobs, plus more tidying in the garden - but these all count as maintenance.
Other than those, we have a cruise holiday booked in March and we're going to a square dance convention for three days in July. Moreover the church is not doing any major work this year as our current grant application is for 2017, so it might be a more relaxed year!
http://www.heyfordhoofers.org.uk/
Sunday, 4 October 2015
Finishing the Summer's Work
Firstly, here's a picture of the finished sash window (upper left window in the picture right). It was a lot of work - probably more than 60 man-hours - but it was worth it simply for the satisfaction of a job well done, plus the appreciation of t'other half!
As I said in August, I'd like to think that the finish on my window is better than the (not so long ago professionally refurbished) window of my neighbour (upper right). Certainly mine was cheaper and still has the glass that it had when I bought it (although two large panes are not original wavy glass).
Apart from the sash window, I have also done the garden (right) along the
side of the house. This is the bit seen from the kitchen window, so it
was really good to get it done before winter.Having moved half a ton of earth from front to back, the side garden was ready for some turf which I acquired from a well known home store. The bit recently done is in front of the shed up to the brick wall. The turf didn't cost the full price as it was quite yellow but, having been down for ten days, it is now indistinguishable in colour from the stuff laid earlier (in three separate phases!) which stretches to the back wall in the distance. NB The grass ramp is to allow me to push the mower up (as the same mower has to do this raised lawn and the front lawn) - I could lift it up now but know that one day soon it will become impossible for me!
I needed a small
amount of top soil to sort out the levels of the last turf beside the shed; this was planned to come from
laying a bit more driveway in front but this job just didn't get done
for ages until happily it all happened suddenly a few weeks ago. The new space (left) is only a small addition but I didn't want to loose too much of the lawn out front. It allows much easier turning of cars in front, as well as a bit more parking when the family visit.On the left is the view from the back of the garden looking along the side of the house. The back gates still need some work but otherwise now everything is just gardening rather than earth-moving, brickwork or stone work. As my wife said, "you did all of that yourself!"
Compare this view with the next picture below, which was taken from pretty well the very same spot.
Here's a couple of reminders of what it looked like just before we bought it:
Firstly (right upper), looking forward from beside the kitchen, from the far end looking forward to where the back gates and my "repaired" wall now are (where the green bin is in the picture):
Secondly (right lower), the view looking to the rear from beside what is now the kitchen window:
The tree (visible in both pictures) beside the wall of the house was a lovely pear tree which sadly had to go. It was so close to the house that a chain saw could not fit between the tree and the wall, but a woodturner friend managed to fell it for me (in exchange for the wood!). Note the concrete path (along the side of the house) which was about six inches above the floor level inside, whereas my black limestone slabs are five inches below the same floor level.
At the time these photos were taken, we had not actually found the side wall of the garden (somewhere to the left of the bottom photo) as the undergrowth was so thick! Eventually (about three months later), to our surprise, we found that the garden widens out as you go back (and our neighbour's garden narrows) - I think it is because it follows a boundary along a mediaeval street, which predated both houses!